In
order to send a Steam Reformer to the Dundalk Marine Terminal for
shipment to Germany, it must be dismantled. The Tower is 12'x17'6"x40'
and weighs 113,000lbs. Along with peripherals, we hauled five trailer
loads to the pier.
Ready for transport, above is the
roof section which is 16' wide and weighs 35,000lbs. Next the tower
must be lifted from its foundation then laid down prior to loading.
(The entire project took place over three weeks.)
|

 
|
| |
Here
we installed milk-processing equipment at a local dairy. Close quarters
are only one of the problems encountered when working in plants.
As this is a dairy, cleanliness is also an isue. Not only do we
move all of the equipment, but perform all process piping and sanitary
welding needed to get the customer up and running in minimal time.
The
cows don't care if the plant is operating or not, they keep producing
milk. |
| We
can also set our Rig-N-Lift 40/60 with a jib boom for handling shears
weighing up to 72,000 lbs. The jib boom allows a lift height of up
to 28'. The
extended counter weight allows us to increase the truck capacity. |
|
| North
American Millwright Services delivers the highest quality service
using the best equipment and qualified professional teams who give
special attention to your schedule and needs. |
|